P09 Β· Due Diligence & Title Verification Β· Karnataka

11E Sketch and Land Survey Karnataka: How to Apply (2026)

What the 11E pre-mutation sketch is, when Karnataka law asks for it, how the Survey, Settlement and Land Records department issues it through Mojini, how it differs from phodi, alienation and hadbasthu sketches, and what a buyer should match it against.

Farmland India Reviewed Β· Official sources linked below
s.131(c)
KLR Act: licensed surveyor sketch for part of a survey number
2006
Year the 11E pre-mutation sketch scheme began
45 days
Upper end of the wait for an 11E, DoLR review 2025
Rs 25
Duplicate 11E sketch within its validity period

When an owner in Karnataka sells only part of a survey number, the piece being sold has to be measured and drawn before the records can split it off. That drawing is the 11E sketch, a pre-mutation sketch prepared by a licensed surveyor and issued by the Survey, Settlement and Land Records department through its Mojini system. It shows the metes and bounds of the portion, so that the Tahsildar can later mutate the RTC (Pahani) for the buyer with its own hissa number.

11E sketch KarnatakaMojini surveyPre-mutation sketchTatkal PhodiHadbasthuLicensed surveyor

What an 11E sketch is

The department introduced the pre-mutation sketch in 2006, and the state then made it compulsory for any mutation arising from a sale, partition or gift of part of a holding, the Comptroller and Auditor General recorded in its 2014 audit of Mojini. The CAG summed up its purpose in one line: "The sketch assures availability of land for mutation." In practice it shows that the seller has the extent he is selling, where he says it is.

Without it, the RTC cannot be split, and a buyer of part of a holding can end up with a registered deed but no separate hissa.

11E, phodi, alienation and hadbasthu

Mojini handles several survey requests that sound alike.

SketchWhen it is neededUsually done by
11E (pre-mutation)Sale, gift or partition of part of a survey numberLicensed surveyor
Phodi and Tatkal PhodiThe RTC has several owners and their hissas are not marked; phodi divides the survey number into sub-numbersLicensed surveyor
Alienation (pre-conversion)Must go with an application to convert agricultural land to non-agricultural useLicensed surveyor
Hadbasthu (boundary demarcation)The owner wants the boundaries of the holding fixed on the groundGovernment surveyor

The order matters. Where a survey number has several owners and no phodi, the sketch for one parcel can be issued only after phodi for the whole survey number is done, the CAG noted. If you need the boundary itself fixed in a dispute, our page on land demarcation explains how that differs from a sale sketch.

The requirement sits in the Karnataka Land Revenue Act, 1964 (Karnataka Act 12 of 1964). Section 128(1) makes anyone acquiring a right in land report it to the village officer within three months, and its third proviso says a person reporting a partition must annex "a sketch showing the metes and bounds" of the land, prepared by a licensed surveyor. Section 131(c) extends this to "any person alienating any land that is part of the survey or sub number", who must get a licensed surveyor's sketch "for the purpose of presenting the deed before the registering authority". Section 18A lets the Director of Survey Settlement and Land Records license surveyors for these purposes. All three came in through Act 14 of 1999, with effect from 30 April 1999.

The courts have limited how far the registration office can push this. In March 2016 a Division Bench of the Karnataka High Court struck down section 22A of the Registration Act as amended for Karnataka and quashed a government circular of 6 April 2009 that had made the 11E sketch a condition for registration, Deccan Herald reported; the ruling is cited as G. Ramachar v. State of Karnataka, AIR 2016 (3) KLJ 1. On 5 October 2021, in Vaishali v. State of Karnataka (W.P. No. 103813/2021, Dharwad Bench), Justice S.R. Krishna Kumar quashed a Sub-Registrar's endorsement that had relied on section 131(c) read with rule 46(h) of the Karnataka Land Revenue Rules, 1966. He directed the state to change the Kaveri registration website so that registered documents could be uploaded without insisting on an 11E sketch.

So a Sub-Registrar cannot refuse to register or return a deed only because no 11E is attached. The sketch still decides whether the part you bought can be mutated and given its own hissa, which is why careful buyers get it before they pay.

What you need before you apply

The landholder applies, so in a sale the seller applies or cooperates. Collect these first.

InputWhere to get it
District, taluk, hobli, villageThe RTC on Bhoomi
Survey number and hissaThe current RTC; older deeds may use a pre-phodi number
Name of the khatedarThe current RTC must show the seller as khatedar
Extent and position of the part being soldThe agreement to sell, with a rough boundary description
Identity of the applicantChecked at the counter or online before the application is accepted

How to apply, step by step

  1. Pull the RTC for the survey number and check that the seller's name, the extent and the hissa match the agreement. If several owners share an unmarked survey number, apply for phodi first.
  2. Apply for the 11E sketch through Mojini, either at the taluk's Nadakacheri (Atal Janasnehi Kendra) counter or online on the department's portal. The department publishes a manual for receiving Mojini applications at the Nadakacheri.
  3. Pay the fee shown at the counter or on the payment screen and keep the receipt with the application number.
  4. Mojini allots the application to a licensed surveyor in turn. The surveyor visits, measures the portion on the ground and prepares the sketch.
  5. The survey office checks and approves the sketch. Track it with the application number in the Search box on bhoomojini.karnataka.gov.in.
  6. Collect the approved 11E, or view it online. Attach it when the deed goes to the Sub-Registrar, and use it for the mutation that follows.

After registration, mutation of the new hissa runs through the Tahsildar's office on Bhoomi. Our mutation guide covers what to watch for once the deed is registered.

Self-survey through Swavalambi

In April 2022 the revenue department ordered a self-survey facility called Swavalambi, Deccan Herald reported. An owner can use it to prepare an 11E, Tatkal Phodi, pre-conversion or partition sketch. The department sends the signed existing sketch of the survey number, the owner draws the division and uploads it with signatures, and the department checks and approves it. The Department of Land Resources' 2025 review of Karnataka's records puts the turnaround at 7 to 10 days, against waits of up to 60 days before.

Fees and timelines

The fee for an 11E depends on the application and shows on the payment screen or counter receipt; the department revised licensed surveyors' service charges and the application rates for 11E, alienation and Tatkal Phodi by circular. A duplicate 11E within its validity period costs Rs 25, under a circular listed on the Mojini portal.

ItemTimeSource
11E or hadbasthu requestUp to 45 daysDoLR evaluation of Karnataka land records, 2025
Phodi division update9 daysSakala timeline, as listed in the same review
Swavalambi self-survey sketch7 to 10 daysSame review
Department's own target for sketches30 daysCAG Report No. 7 of 2014, para 4.3.6

The 2014 audit found an average of 92 days against that 30-day target. Book the sketch before you fix a registration date.

!

Match the sketch to the deed schedule

The extent, the boundaries on all four sides and the survey and hissa numbers in the 11E should be copied into the sale deed schedule word for word. If the deed says one area and the sketch another, settle the difference with the seller before registration, not after.

What an 11E sketch does not prove

  • Title. It measures the land the seller holds on the RTC. It does not trace how he got it; that needs a 30-year title search.
  • Charges and cases. Mortgages and suits are outside it. An encumbrance certificate and a court case search cover those.
  • Conversion or layout approval. An 11E for a part of farmland says nothing about whether it may be used for building. That needs the separate alienation sketch and a conversion order.
  • Road access. A sketch can draw a piece with no path to a road. Check access and easement before you choose which part to buy.

Red flags for a buyer

Watch for an 11E in the name of someone who is not the khatedar on the current RTC, a sketch for a survey number with several owners and no phodi, an extent on the sketch that is smaller than the deed, and a sketch so old that its validity period has run out. A seller who offers the 11E "after registration" is passing his measurement risk to you. Our page on reading land area in a sale deed helps with the schedule.

A Doddaballapur sale in 2023

In 2023, Suresh Hegde, a Pune engineer, agreed to buy 1.5 acres out of a 4.2-acre survey number near Doddaballapur in Bengaluru Rural district for Rs 54 lakh. The RTC showed the seller's share, and the agent offered to have the sketch made after registration.

Suresh insisted on the 11E first. The licensed surveyor measured the portion between the seller's mango trees and the cart track at 1.32 acres, because a neighbour's fence sat inside the old line. The price came down to Rs 47.5 lakh, the deed schedule was redrawn from the sketch, and the mutation went through in the buyer's name with a new hissa number.

Frequently Asked Questions

What is an 11E sketch in Karnataka?
11E is the pre-mutation sketch. A licensed surveyor measures and draws the part of a survey number being sold, gifted or partitioned, and the Survey, Settlement and Land Records department issues it through Mojini.
Is the 11E sketch mandatory for registration in Karnataka?
No. The Karnataka High Court quashed the 2009 circular in 2016 and in 2021 ordered the Kaveri website to accept deeds without it. It is still needed to mutate and split the RTC.
Who prepares an 11E sketch?
Licensed surveyors. Section 18A of the Karnataka Land Revenue Act lets the Director of Survey Settlement and Land Records license surveyors for this work.
How long does an 11E sketch take?
45 days at most, according to the Department of Land Resources' 2025 review. A Swavalambi self-survey sketch takes 7 to 10 days.
What is the fee for a duplicate 11E sketch?
Rs 25, for a duplicate within the sketch's validity period, under a department circular. The fee for a fresh 11E shows at payment.
What is the difference between 11E and phodi?
Phodi divides a jointly held survey number into hissas. An 11E draws the part being transferred, and it can be issued only after phodi where hissas are unmarked.
Where do I check the status of an 11E application?
bhoomojini.karnataka.gov.in. Enter the application number in the Search box on the home page.

Sources

This is general information on the procedure, not legal advice for your situation. Have a local advocate read the RTC, the 11E sketch and the deed schedule together before you pay. Corrections: wiki@farmlandindia.com.

For land buyersMap Layers coming soon

See every listing on the map

View on mapEvery listing pinned where it actually is. Master plans, survey numbers and boundaries are coming. Β· Browse the list
For land owners

Own land? List it free. Our team calls within 24 hours.

Free for owners, families, lawyers and agents. We review the documents you share before it goes live; they are never published. Use the form

Related reading

Title Search Report: Contents, Issuer and Cost (2026)
P09 Due Diligence & Title Verification

Title Search Report: Contents, Issuer and Cost (2026)

What an advocate's title search report covers, how the Sub-Registrar search under the Registration Act works, how banks rely on it and what the official search and copy fees are.

10 min read27 Nov 2026
How to Verify Land Title in India: Full Guide
P09 Due Diligence & Title Verification

How to Verify Land Title in India: Full Guide

What "clear title" really means, why 30 years is the standard, and the red flags a title search must catch before you buy land in India.

29 Oct 2026
The 12-Step Land Due Diligence Checklist India
P09 Due Diligence & Title Verification

The 12-Step Land Due Diligence Checklist India

Every step to verify before buying land in India β€” ownership, title chain, EC, litigation, RERA, and registration. The full buyer's checklist.

29 Oct 2026
← All P09 Due Diligence & Title Verification guides

Farmland India ("the Platform"), operated by Bulk Procure Private Limited, is a digital marketplace for listing agricultural land, farmhouse and plotted development projects. The Platform is not a real estate broker, agent or intermediary under RERA or any other applicable law, and does not act for either party to a transaction.

Listings are submitted by developers, owners and their authorised representatives. Before publication, the Platform carries out a documentary review of the material supplied and records what was sighted. That review is limited to the documents made available to us at that time. It is not a title investigation, not a legal opinion, and not a warranty of title, approvals, or the accuracy of any information supplied by a lister. The Trust Score is an internal assessment produced from that review and is intended as a research aid, not as a guarantee of outcome.

Every buyer must carry out independent due diligence before any transaction β€” including verification of land records, encumbrance searches, approvals and regulatory compliance β€” through their own advocate and chartered accountant. Any legal or advisory professional introduced through the Platform is engaged directly by the user, on that professional's own terms; the Platform does not employ, supervise or accept responsibility for their work.

Nothing on the Platform is investment advice. Land values can fall as well as rise. The Platform is not liable for any loss, dispute or damage arising from a transaction between parties.