Farmland India
P22 · Industrial Land & Parks · Haryana · All districts

HSIIDC Industrial Estates of Haryana: 2026-27 Reserve Prices and EMP-2015 Rules

Every HSIIDC estate and IMT with its 2026-27 rate per Sq.Mt. and Sq.Yd., estate categories, and the rules on allotment, construction deadlines, transfer, leasing and resumption.

Farmland India Reviewed · Updated 14 November 2026 · Official sources linked below
Rs 6,600–1,28,500
2026-27 range per Sq.Mt.
53
Priced entries in the 2026-27 lists
3 + 2 years
To complete the project
Rs 300
Category A transfer fee per Sq.Mt.

HSIIDC (Haryana State Industrial and Infrastructure Development Corporation) develops and allots industrial plots across Haryana: Industrial Model Townships (IMTs) such as Manesar and Kharkhoda, older Industrial Estates such as Udyog Vihar Gurugram and Kundli, and estates transferred to it from HSVP. This hub lists every estate in HSIIDC's FY 2026-27 rate list with its price per Sq.Mt. and Sq.Yd., and explains the Estate Management Procedures (EMP-2015) that govern allotment, construction deadlines, extension, transfer, leasing, surrender and resumption. Every figure links to an HSIIDC document.

hsiidc industrial estateshsiidc plot rate 2026-27hsiidc reserve pricehsiidc e-auctionhsiidc industrial plothsiidc emp 2015hsiidc transfer feehsiidc extension feehsiidc resumptionharyana industrial plot rateimt manesar rateie gurugram udyog vihar ratehsiidc category a estateshsiidc estate listhsiidc leasing ruleshsiidc project completion periodhsiidc surrender of plothsvp industrial estates hsiidcindustrial land haryanahsiidc processing feehsiidc resale plot transferheep 2020 blocks

1. At a glance

ItemDetailSource
Who allotsHSIIDC, a Haryana Government undertakingHSIIDC
Highest 2026-27 rateIE Gurugram and Gurugram Pace City: Rs 1,28,500 per Sq.Mt.HSIIDC land rates 2026-27
Lowest 2026-27 rateTohana: Rs 6,600 per Sq.Mt.HSIIDC land rates 2026-27
Rates pendingIMT Bawal, Kundli, Mega Food Park Rai, I.E. Kalka (auction from 30.03.2026 not yet finalised)HSIIDC land rates 2026-27, note iv
How general plots are soldE-auction from a reserve priceEMP-2015 Chapter 3
Token money5% of plot cost at reserve priceEMP-2015 Chapter 3
Time to complete the project3 years from offer of possession, plus up to 2 paid yearly extensionsEMP-2015 clauses 5.1, 5.2, 5.5
Transfer fee (Category A / B / C)Rs 300 / Rs 150 / Rs 50 per Sq.Mt.EMP-2015 clause 8.7

2. What HSIIDC runs

  • Industrial Model Townships (IMTs). Large planned townships: Manesar, Bawal, Rohtak, Faridabad, Kharkhoda and Sohna. Each has its own guide, linked below.
  • Industrial Estates (IEs). HSIIDC's Industrial Estates page lists estates such as Udyog Vihar Gurugram, Faridabad, Kundli, Rai, Barhi, Bahadurgarh, Dharuhera, Karnal, Manakpur, Yamunanagar, Sonepat, Panipat, Narnaul, Growth Centre Saha, Roz-Ka-Meo, IIDC Sirsa, Barwala, Ambala, Tohana and Jind. HSIIDC describes an industrial estate as a development of up to 1,500 Acre.
  • Estates transferred from HSVP. Industrial sectors first developed by HSVP (formerly HUDA) in Panchkula, Faridabad, Gurugram, Karnal, Panipat, Hisar, Bhiwani, Rewari, Dharuhera, Bahadurgarh and other towns are now managed by HSIIDC and carry their own reserve prices.
  • Theme parks and sheds. IT Parks (Panchkula, Manesar, Rai), the Mega Food Park at Rai, sheds at the Barhi Food Park and flatted factories in Faridabad.

HSIIDC also handles plots in estates developed by the state Industries Department. Whatever the estate, the same rule book applies: the Estate Management Procedures, EMP-2015, as amended by HSIIDC's Board.

3. Category A, B and C estates

EMP-2015 groups estates into three categories. The category decides the processing fee, extension fee and transfer fee. It follows the block classification in the Haryana Enterprises and Employment Policy (HEEP) 2020: Block A estates are Category A, Block B are Category B, and Blocks C and D are Category C. EMP-2015 gives this indicative list:

CategoryHSIIDC estates and IMTsHSVP estates now with HSIIDC
AAmbala, Faridabad, Gurugram, Manesar, Bahadurgarh, Panchkula, Bawal, Dharuhera, Barhi, Kundli, Murthal, Rai, Sonipat, Manakpur, YamunanagarFaridabad, Gurugram, Bahadurgarh, Panchkula, Panipat, Dharuhera, Murthal
BKarnal, Kalka, Panipat, Samalkha, Kutana, Rohtak, Kharkhoda, WHTH Patli Hazipur, Farukh NagarHisar, Karnal, Kurukshetra, Palwal, Rewari, Rohtak
CAll other estatesAll other estates

The Industries Department's own estates in Ambala, Gurugram, Bahadurgarh, Panipat, Sonipat and Yamunanagar are Category A, and those in Hisar, Karnal, Kohand, Nelokheri, Palwal and Pinjore are Category B. HSIIDC's Board can revise the list.

4. FY 2026-27 reserve prices: HSIIDC estates

HSIIDC's Land Rates page publishes the rates for 2026-27 under the heading "Recommended Reserve Price for Approval of MD", in rupees per Sq.Mt. We have added a per Sq.Yd. column (rate divided by 1.19599, rounded). In an e-auction this is the floor; the final price is the winning bid.

Estate or IMTPer Sq.Mt.Per Sq.Yd.
IE Gurugram (Udyog Vihar Phase I–VI, Sector 34–35)Rs 1,28,500Rs 1,07,440
Faridabad Sector 31Rs 73,000Rs 61,040
IMT Manesar (Phase I–V), TPT Hub, WHTHRs 68,800Rs 57,530
Faridabad Sector 59Rs 65,700Rs 54,930
IT Park Panchkula, for developersRs 63,700Rs 53,260
IT Park Panchkula, for self usersRs 53,100Rs 44,400
IMT FaridabadRs 49,800Rs 41,640
Karnal (Phase I–III)Rs 46,800Rs 39,130
I.E. Panchkula Phase IRs 43,600Rs 36,460
IMT KharkhodaRs 42,700Rs 35,700
Bahadurgarh (Sectors 16, 17, 4B, 8 and 8A)Rs 42,500Rs 35,540
Barwala (Phase I–II)Rs 40,000Rs 33,450
IE DharuheraRs 33,300Rs 27,840
Barhi (Phase I–III)Rs 30,000Rs 25,080
SamalkhaRs 29,700Rs 24,830
Yamuna Nagar Phase I and II, IIDCRs 29,300Rs 24,500
NarnaulRs 28,900Rs 24,160
SonipatRs 28,900Rs 24,160
Roz-Ka-MeoRs 28,600Rs 23,910
SirsaRs 28,000Rs 23,410
MurthalRs 25,300Rs 21,150
IMT Rohtak (Phase I–III)Rs 24,800Rs 20,740
IMT SohnaRs 24,700Rs 20,650
Karnal (Sector 37)Rs 24,600Rs 20,570
PanipatRs 23,900Rs 19,980
Manakpur Phase IIRs 21,300Rs 17,810
Ambala CanttRs 21,200Rs 17,730
Saha Phase IRs 20,300Rs 16,970
Kutana, RohtakRs 17,500Rs 14,630
NarwanaRs 16,000Rs 13,380
JindRs 14,700Rs 12,290
Saha Phase IIRs 14,500Rs 12,120
Manakpur Phase IRs 11,600Rs 9,700
TohanaRs 6,600Rs 5,520
IMT Bawal (Phase I–IV)Not yet fixed—
Kundli (Phase I–V)Not yet fixed—
Rai (Phase I–III)Not yet fixed—
KalkaNot yet fixed—
  • Sheds and flatted factories: flatted factories in Faridabad Rs 46 lakh per unit; sheds at the Barhi Food Park Phase III Rs 92 lakh (ground floor) and Rs 80.50 lakh (first floor).
  • IT Parks at Manesar and Rai: 15% above the estate's industrial rate for self users and 30% above for developers.
  • Pending estates: HSIIDC says the auction for IE Kundli, IMT Bawal, Mega Food Park Rai and I.E. Kalka held from 30 March 2026 had not been finalised, and their reserve prices will be revised once bids are accepted and payments made.
!

Reading the rate list

The 2026-27 rate is the starting point for the next auction, not what an existing allottee paid. Resale plots trade at market prices, which can be well above or below these figures. Prices are subject to change and availability.

5. FY 2026-27 reserve prices: estates transferred from HSVP

EstatePer Sq.Mt.Per Sq.Yd.
Industrial Area Phase I and II, PanchkulaRs 1,11,000Rs 92,810
Gurugram Pace CityRs 1,28,500Rs 1,07,440
Faridabad Sector 58Rs 75,800Rs 63,380
Faridabad Sector 31Rs 73,000Rs 61,040
Faridabad Sector 59 Phase IRs 65,700Rs 54,930
KarnalRs 61,500Rs 51,420
Bahadurgarh MIE Part A and BRs 53,800Rs 44,980
Faridabad Sector 59 Phase II and part Phase IIRs 47,400Rs 39,630
HisarRs 46,000Rs 38,460
Panipat Sector 25 I and IIRs 42,900Rs 35,870
Panipat Sector 29 I and IIRs 38,600Rs 32,270
Faridabad (all other sectors)Rs 37,700Rs 31,520
Panipat Sector 29, dyeing unitRs 35,400Rs 29,600
BhiwaniRs 35,200Rs 29,430
DharuheraRs 34,000Rs 28,430
Roz-ka-MeoRs 30,800Rs 25,750
SirsaRs 28,000Rs 23,410
MurthalRs 25,300Rs 21,150
RewariRs 23,500Rs 19,650

HSIIDC notes that HSVP's own reserve prices for 2023-24 to 2026-27 were not available, so it took HSVP's 2018-19 price and added 10%. Where 2018-19 figures were missing it used 2015-16. For Faridabad's 18 sectors, rates existed for only two sectors and were used as the base for the rest. For Murthal it took the higher of the collector rate and HSIIDC's rate, and Gurugram Pace City uses the rate of HSIIDC's nearby Udyog Vihar Phase VI.

6. Which estate suits which buyer

If you needLook at2026-27 rate per Sq.Mt.
Delhi–Gurugram address, services or light assemblyIE Gurugram (Udyog Vihar)Rs 1,28,500
Large auto or engineering unit on NH-48 and KMPIMT ManesarRs 68,800
Faridabad–Palwal belt on NH-19IMT Faridabad, Faridabad Sectors 31, 58 and 59Rs 49,800 to Rs 75,800
Newer IMT on KMP near Delhi's westIMT KharkhodaRs 42,700
Footwear, plastics and light engineering west of DelhiBahadurgarhRs 42,500 (HSIIDC) to Rs 53,800 (MIE)
Lower land cost on NH-44Panipat, Samalkha, Murthal, Sonipat, BarhiRs 23,900 to Rs 30,000
Lower land cost south of GurugramIMT Sohna, Dharuhera, RewariRs 23,500 to Rs 34,000
Lowest land cost, room to growIMT Rohtak, Kutana, Saha, Jind, Narwana, TohanaRs 6,600 to Rs 24,800

Each of these has a detailed guide: IMT Manesar, IMT Kharkhoda, IMT Faridabad, IMT Rohtak, IMT Sohna, IMT Bawal, Bahadurgarh, NH-44 Panipat–Karnal, Ambala–Yamunanagar–Panchkula.

7. How HSIIDC allots plots here

  1. Watch for the notice. HSIIDC publishes each e-auction for HSIIDC estates on its advertisements page, with plot sizes, reserve price, token money and dates. General-category notices do not list plot numbers.
  2. Register and pay the token money. Bidders register online within the advertised window and deposit token money of 5% of the plot cost at reserve price, as Chapter 3 of EMP-2015 requires.
  3. Bid. The plot goes to the highest bid above the reserve price, subject to HSIIDC accepting it.
  4. Pay and take possession. The payment schedule and possession terms follow the notice and HSIIDC's Estate Management Procedures (EMP-2015, with amendments up to 31.12.2025).
  5. Build and start production on time. EMP-2015 sets the period for completing the project and starting business, the extension rules, and when HSIIDC can resume an unused plot.

HSIIDC's own estate pages point buyers to EMP-2015 for the mode of allotment, possession, project completion period, surrender and resumption, leasing and renting, and transfers. Read the version on the HSIIDC EMP page before you bid. Our upcoming HSIIDC guide covers these rules in detail.

!

Check a plot's status before a resale deal

HSIIDC's e-Sewa dashboard shows plot status for allottees. For a resale plot, ask the seller for the allotment letter, payment status and any resumption or extension notices, and get HSIIDC's transfer approval before you pay in full.

8. Allotment rules and payment terms that apply to HSIIDC estates

HSIIDC allots industrial plots under Chapter 3 of its Estate Management Procedures (EMP-2015). The points below are from the version of Chapter 3 published on HSIIDC's Mode of Allotment page (file dated November 2023). Check the advertisement for any later change.

  • General category plots go only by e-auction. HSIIDC advertises plot sizes by estate without plot numbers. You register for an estate and plot size, and HSIIDC announces how many plots it will offer at least 48 hours before the auction.
  • How the auction runs. Bidding runs from 7.00 am to 9.00 pm. Round 1 runs from 7.00 am to 11.00 am and later rounds last 10 minutes, extended by 10 minutes whenever a bid comes in during the last five minutes. The top bidder in each round gets 10 minutes to choose a plot.
  • HSIIDC can reject any bid. The Managing Director may accept or reject any bid, including the highest, before allotment.
  • Land should not dominate the project. The value of land should preferably not exceed 60% of the total fixed capital investment, and plant and machinery should be at least 20% of it.
  • Mega and FDI projects. Plots of one Acre and above can be offered to mega projects and 100% FDI projects through advertisement; if several applicants want the same land, it goes to auction.
  • Service enterprises. Up to 25% of plots in an estate may be earmarked for services that support manufacturing, such as test labs, tool rooms, R&D, weighbridges and vehicle repair.
  • No enhancement for new allottees. Plots allotted after EMP-2015 came into force are not charged proportionate enhancement for court-ordered increases in land compensation after the RLA.
  • Conveyance deed. You get the conveyance deed after paying the full price and clearing all dues. For NRI or PIO allottees, the money must come from an NRE account or remittances from abroad.

Payment schedule

StageWhat you payWhen
Registration for the e-auction5% of the plot cost at reserve price (token money)Within the 15-day registration window in the advertisement
After you win10% of the plot price at your winning (H-1) bidWithin 72 hours of HSIIDC accepting the bid; otherwise the 5% is forfeited
After the Regular Letter of Allotment (RLA)15% of the plot priceWithin 30 days, extendable by 30 days with 15% a year interest
Second instalmentA further 25%Within 60 days of the RLA
Balance50%Lump sum within 90 days (10% rebate on that 50%), or four half-yearly instalments over two years with 12% a year interest from the offer of possession
Full payment optionBalance 75% at onceWithin 45 days of the RLA, with a 10% rebate on plot cost

Interest at 12% a year applies to the balance after the offer of possession, and defaults attract 15% a year, compounded half-yearly. Paying off the outstanding plot cost in a lump sum at any stage earns a 3% rebate on the principal outstanding.

Processing fee (non-refundable, GST included)

Plot size (Sq.Mt.)Category 'A' estatesCategory 'B' and 'C' estates
Up to 500Rs 5,000Rs 3,000
501–1,050Rs 7,500Rs 5,000
1,051–4,050Rs 10,000Rs 7,500
4,051–8,100Rs 15,000Rs 10,000
8,101 and aboveRs 25,000Rs 15,000
!

A leasehold route for larger projects

Chapter 3 also sets out a leasehold option for plots of half an Acre (1,800 Sq.Mt.) and above, for companies shifting manufacturing to India, projects with at least 50% FDI, or import-substitution projects in thrust sectors. The upfront premium is bid in an e-auction from a reserve of 20% of the allotment price, annual rent is 6% of the allotment price, and the lease can be converted to freehold. Minimum investment is Rs 10 crore for plots up to one Acre and Rs 25 crore above that. The policy was stated to apply initially for one year, so ask HSIIDC whether it is still open.

9. Offer of possession

Under Chapter 4 of EMP-2015, HSIIDC offers physical possession only after basic infrastructure is ready at the site. For estates planned after 8 March 2017 this means:

  • A motorable access road to the plot.
  • A water connection at the site for construction and drinking.
  • A sewerage disposal network.
  • Electrical distribution for construction. Industrial-grade supply is to be available before the first occupation certificate.
  • Security in the estate, such as a police post.

A committee including the Estate Manager, an independent director and a representative of the industrial association certifies the infrastructure before possession is offered. The offer letter goes by registered post, speed post or email with the plot's zoning plan. If the plot is encumbered or basic amenities are missing, you can object within 30 days of the offer letter, with evidence.

!

Why the possession date matters

Your three-year clock for completing the project starts from the date of offer of possession, not the date you take it. Keep the offer letter and the date safe.

10. Deadline to build and start production

  • Plots: complete the project within three years of the offer of possession (clause 5.1).
  • Sheds and flatted factories: two years from the offer of possession, extendable by two more years (clause 5.3).
  • Extensions: beyond the first three years, the period is deemed extended year by year for two more years when you pay the extension fee online (clause 5.2). Late payment carries 12% a year interest (clause 5.4).
  • Hard stop: no extension beyond the fifth year from allotment or offer of possession, whichever is later. The plot is then liable to resumption with any structure on it, or to a mandatory auction if you choose that (clause 5.5).
  • Deemed approval: the Estate Manager must decide an extension request within 30 days. If you get no reply in that time, the extension is deemed granted (clause 5.5).

Extension fee (clause 5.7)

Category of estate1st extension (4th year), per Sq.Mt.2nd extension (5th year), per Sq.Mt.
Category ARs 50Rs 50
Category BRs 25Rs 25
Category CRs 10Rs 10

For sheds the fee is charged on the plot area under the shed; for flatted factories on the plinth area.

What counts as a completed project (clause 5.8)

  • Minimum construction: 25% of the permissible covered area (PCA) for plots up to one Acre (4,050 Sq.Mt.); 20% for plots above one Acre up to five Acre; 15% above five Acre.
  • Production: the unit must have started commercial production after installing plant and machinery worth at least 30% of the value prescribed for the allotment.
  • Building rules follow the Haryana Building Code 2017; where EMP-2015 and the Code differ, the Code prevails (clause 5.11).

HSIIDC's Board has also granted one-off relief for older allottees. In November 2024 it allowed allottees of plots allotted on or before 31 December 2020, whose maximum period expired on 31 December 2024, one more year to 31 December 2025, if they had building plans approved or submitted by 30 June 2024 and had started construction by 31 October 2024. The fee was 2% of the current reserve price with an occupation certificate and 4% without one.

We read EMP-2015 as amended up to HSIIDC's 383rd Board meeting (November 2024). HSIIDC has since posted a version with amendments up to 31 December 2025 on its EMP page; check any clause you rely on against that version.

11. Selling or transferring an HSIIDC plot

Plots are allotted freehold, but EMP-2015 Chapter 8 says the freehold is restrained by the allotment conditions. Every transfer, first or later, needs HSIIDC's prior written permission.

  • First transfer, standard route: the original allottee must have paid the full price including any enhanced cost, executed the conveyance deed, obtained the occupation certificate and completed the project, and have no dues (clause 8.5).
  • Exempt transfers: inheritance, a will, transfers within the family, succession on death, and takeover by banks or financial institutions are allowed without these pre-conditions. The transferee must implement the approved project (clause 8.5 ii). Family transfers do not apply to NRI or disability-category allotments.
  • NRI and disability-category plots: for allotments made on or after 22 August 2019, these can be transferred only to an NRI or a person with a disability respectively.
  • Later transfers: once the project is complete and the transfer fee has been paid on an earlier transfer, a later buyer pays only the processing fee and signs an agreement with HSIIDC (clause 8.6).

Transfer fee (clause 8.7)

Category of estateTransfer fee per Sq.Mt. of plot
Category ARs 300
Category BRs 150
Category CRs 50

GST is extra. For sheds the fee is on the plot area under the shed, and for flatted factories on the plinth area.

Transferring a general-category plot before the project is complete

SituationAllotted before EMP-2015Allotted under EMP-2015
Occupation certificate obtained, project not implementedDouble the normal transfer feeNormal transfer fee
First transfer of a vacant or unused plot (no occupation certificate)10% of current allotment price, or double the transfer fee if higher2% of current allotment price, or double the transfer fee if higher
Later transfer after the transferee completes the projectProcessing feeProcessing fee
Later transfer of a vacant or unused plot5% of current allotment price, or double the transfer fee if higher2% of current allotment price, or double the transfer fee if higher
  • The seller must have paid the full price and executed the conveyance deed first. The buyer must finish the project within the original period, or the extended period on payment of the extension fee.
  • Transferring without prior permission attracts a penalty equal to the normal transfer fee. Transfer fees carry 12% a year interest from the date of transfer, or from the date of the request where the fee is linked to the current allotment price.
  • After a Provisional Transfer Letter, its conditions must be met within 120 days; delay costs 25% of the normal transfer fee.
  • If the deal falls through after the transfer fee is paid, HSIIDC refunds it after keeping GST and the processing fee.
!

Buying a resale plot

Ask the seller for the allotment letter, conveyance deed, occupation certificate and the e-Sewa ledger. Work out which transfer-fee row applies before you agree a price, because a vacant plot transferred under EMP-2015 costs at least 2% of the current allotment price in fees.

12. Leasing out built premises

  • You can lease premises built on an industrial plot or shed only after getting the occupation certificate (clause 7.1). Prestigious-category projects can lease after part or full completion.
  • An empty plot cannot be leased.
  • Besides manufacturing, EMP-2015 allows leasing to support services such as machinery repair, test labs, industrial photography, bulk courier, weighbridges, CAD and design services, R&D, tool rooms, printing and publishing, industrial kitchens, engineering services, vehicle servicing without showrooms, ATMs and equipment rental.
  • Leasing to technical training and skill development centres needs HSIIDC's prior written permission (clause 7.2).

13. Surrender, resumption and appeal

Surrendering a plot

Allottees can surrender a plot at any time. HSIIDC refunds the money paid towards the plot's principal and enhanced cost, without interest, after deducting 10% of the plot price (clause 6.1). Read the full clause for how interest already paid is treated.

When HSIIDC can resume a plot

  • Non-payment of the plot price, enhanced cost, extension fees, transfer fees, leasing fees, penalties, or maintenance and other charges.
  • Not completing the project within the permitted period.
  • Breaking any other condition of allotment.

Before resumption the Estate Manager issues a notice giving one month to fix the breach or to authorise HSIIDC to sell the plot by auction (clause 6.2). If the plot is auctioned at the allottee's option, the ex-allottee can receive a premium over the refund amount once the auction buyer has paid in full.

Appeal and restoration

  • An appeal against a resumption order passed by the Managing Director lies with the Administrative Secretary of the Industries Department, within 90 days (clause 6.3).
  • The Appellate Authority can hear the appellant and may offer re-allotment at the current allotment rate.
  • Where a plot was resumed only for unpaid enhanced cost, maintenance or water and sewer charges, it can be restored once the default is cleared. Up to Rs 25 lakh the Estate Manager decides; larger amounts go to more senior officers.
!

Legal questions

Resumption and restoration turn on the facts of each case. This page summarises HSIIDC's rules; it is not legal advice. Take advice from a lawyer before you reply to a resumption notice.

14. HSIIDC plot or private licensed colony?

HSIIDC estate plotPrivate licensed colony (HRERA)
How you buyE-auction or allotment noticeDirect booking with the developer
PriceReserve price is a floor; final price set by biddingDeveloper's price list
After purchaseEMP-2015 rules on project completion, transfer and useFewer post-sale conditions; conveyance deed from the developer
InfrastructureBuilt and maintained by HSIIDCBuilt by the developer; check RERA completion date
Plot sizesSet by the estate layout; often largerOften smaller, from a few hundred Sq.Yd.

15. Talk to our industrial land team

Farmland India's industrial land team can shortlist parks across Haryana by plot size, budget and pollution category, and line up site visits. Browse industrial parks listed on Farmland India or compare nearby belts: Manesar–KMP, Kharkhoda, Sohna–Ballabgarh, Rohtak NH-152D.

Frequently Asked Questions

What is the HSIIDC industrial plot rate for 2026-27?
Rates range from Rs 6,600 per Sq.Mt. at Tohana to Rs 1,28,500 per Sq.Mt. at IE Gurugram (Udyog Vihar). IMT Manesar is Rs 68,800, IMT Faridabad Rs 49,800 and IMT Kharkhoda Rs 42,700. HSIIDC labels these as recommended reserve prices for approval of the Managing Director.
Why are IMT Bawal, Kundli, Rai and Kalka missing from the rate list?
HSIIDC says an auction for these four estates held from 30 March 2026 had not been finalised, and their reserve prices will be revised after bids are accepted and payments are made.
How do I convert HSIIDC's rate to Sq.Yd.?
Divide the per Sq.Mt. rate by 1.19599. For example, IMT Manesar's Rs 68,800 per Sq.Mt. is about Rs 57,526 per Sq.Yd.
How long do I get to build on an HSIIDC plot?
Three years from the offer of possession, extendable year by year for two more years on payment of the extension fee. No extension is allowed beyond the fifth year from allotment or possession offer, whichever is later.
What is the HSIIDC extension fee?
Rs 50 per Sq.Mt. a year in Category A estates, Rs 25 in Category B and Rs 10 in Category C, for the fourth and fifth years.
What is the HSIIDC transfer fee?
Rs 300 per Sq.Mt. in Category A estates, Rs 150 in Category B and Rs 50 in Category C, plus GST. Higher charges apply when a vacant or incomplete plot is transferred.
Can I sell an empty HSIIDC plot?
Yes, for general-category plots, once the full price is paid and the conveyance deed executed. For plots allotted under EMP-2015, the fee is 2% of the current allotment price or double the transfer fee, whichever is higher, and the buyer must still finish the project in time.
Can I rent out my HSIIDC plot?
Only premises built on it, and only after the occupation certificate. An empty plot cannot be leased.
Which HSIIDC estates are Category A?
EMP-2015 lists Ambala, Faridabad, Gurugram, Manesar, Bahadurgarh, Panchkula, Bawal, Dharuhera, Barhi, Kundli, Murthal, Rai, Sonipat, Manakpur and Yamunanagar among HSIIDC estates, in line with Block A of HEEP-2020.
What happens if I surrender an HSIIDC plot?
HSIIDC refunds the principal and enhanced cost paid, without interest, after deducting 10% of the plot price.
Does Farmland India sell HSIIDC plots?
No. HSIIDC allots its plots directly through e-auctions. Our industrial land team can explain the terms and help you compare HSIIDC, RIICO and private options.

Sources

Spotted an error? Write to wiki@farmlandindia.com and we will correct it.

Looking for an industrial plot?

Tell us your plot size, budget and pollution category. Our industrial land team will shortlist parks and arrange site visits.

Related reading

From the blog

← All P22 Industrial Land & Parks guides

Farmland India ("the Platform"), operated by Bulk Procure Private Limited, is a digital marketplace for listing agricultural land, farmhouse and plotted development projects. The Platform is not a real estate broker, agent or intermediary under RERA or any other applicable law, and does not act for either party to a transaction.

Listings are submitted by developers, owners and their authorised representatives. Before publication, the Platform carries out a documentary review of the material supplied and records what was sighted. That review is limited to the documents made available to us at that time. It is not a title investigation, not a legal opinion, and not a warranty of title, approvals, or the accuracy of any information supplied by a lister. The Trust Score is an internal assessment produced from that review and is intended as a research aid, not as a guarantee of outcome.

Every buyer must carry out independent due diligence before any transaction — including verification of land records, encumbrance searches, approvals and regulatory compliance — through their own advocate and chartered accountant. Any legal or advisory professional introduced through the Platform is engaged directly by the user, on that professional's own terms; the Platform does not employ, supervise or accept responsibility for their work.

Nothing on the Platform is investment advice. Land values can fall as well as rise. The Platform is not liable for any loss, dispute or damage arising from a transaction between parties.