PADMA Scheme Haryana: Block-Level MSME Clusters, Grants and How They Work

Haryana's PADMA programme explained from the state's notifications: cluster grants of 50–85%, land rules, unit incentives, plot rules and how to apply.

Farmland India Reviewed · Updated 27 November 2026 · Official sources linked below
143
Blocks with a planned cluster
50–85%
Grant to build a cluster
Rs 45 cr
Maximum PCIDS grant
25 Acre
Minimum cluster in most blocks

PADMA, the Programme to Accelerate Development for MSME Advancement, is Haryana's plan to put a small industrial cluster in every one of its 143 blocks, each built around a product the block is already known for. It pays for two things: grants of 50% to 85% to whoever builds a cluster, and subsidies to micro and small units that set up inside one. This guide sets out the rules from the state's notifications, what they mean for a landowner or developer and for a manufacturer looking for a plot, and how PADMA sits next to HSIIDC estates. Last checked against official sources on 27 November 2026.

padma scheme haryanapadma yojana haryanapadma haryana msmepadma cluster haryanaone block one product haryanapadma cluster infrastructure development schemepcids haryanamsme cluster haryanaharyana industrial park schemepadma capital subsidypadma interest subsidypadma industrial parkhsiidc padmaprivate industrial park haryanaharyana block industrial clusterpadma scheme eligibilitypadma scheme applyharyana msme scheme 2026

1. Key facts

ItemDetailSource
ProgrammeProgramme to Accelerate Development for MSME Advancement (PADMA), 'One Block One Product'Haryana MSME Directorate
NotifiedPolicy first notified 29 November 2022; revised notification 17 August 2023Haryana Assembly reply; Gazette
AimA new MSME cluster in each block, about 4,000 Acre in all; 10,000+ enterprises; 3,00,000 jobsPADMA notification
Cluster size25 to 100 Acre per block; minimum 25 Acre (15 Acre in D-category blocks under PCIDS)PADMA notification; PCIDS
Infrastructure grant50% (B blocks), 75% (C), 85% (D); up to Rs 35 crore (≤50 Acre) or Rs 45 crore (>50 Acre)PCIDS, 4 March 2024
Unit incentives in clusters30% capital subsidy (max Rs 30 lakh); 6% interest subsidy (max Rs 20 lakh a year); branding supportPADMA notification
BudgetRs 1,000 crore earmarked in the 2023-24 budgetPADMA notification
Scheme windowPCIDS runs 17.08.2023 to 16.08.2028 or the policy's validityPCIDS

2. What PADMA is, in plain terms

Most Haryana industry sits in a handful of districts near Delhi. PADMA tries to spread it out. The MSME Directorate describes it as 'One Product, One Block': each block has a product picked for it, and the cluster in that block is meant to serve units making that product.

  • Clusters, not single plots: the unit of PADMA is a park of 25 Acre or more with shared facilities, built by HSIIDC or by a private or public implementing agency.
  • Grants for builders: the PADMA Cluster Infrastructure Development Scheme (PCIDS) pays part of the cost of roads, utilities and common facilities.
  • Incentives for units: micro and small units inside a PADMA cluster get capital and interest subsidies and help with branding and marketing.
  • Product rule: plots in a PCIDS-funded cluster may only be sold or leased to MSMEs making the block's approved product.

3. Who builds PADMA clusters

The PADMA notification gives HSIIDC the job of identifying land, building basic and common infrastructure, building sheds for lease and allotting plots, using its own funds and the state's SIIDS scheme. PCIDS then opens the door to others as Implementing Agencies:

  • Public or private companies, joint ventures, partnerships and LLPs.
  • Societies, trusts, cooperatives and Farmer Producer Organisations.
  • Government agencies.
  • Preference goes to women-led and SC-led implementing agencies.
Condition for an Implementing AgencyDetail
Own contributionAt least 10% of total project cost as equity or contribution
Bank loanA term loan of at least 5% of the project cost from a bank, NBFC or financial institution
Net worthAt least 1.5 times the grant sought (promoters' combined net worth counts)
RecordNot a wilful defaulter or debarred by any government agency
LandOwned or on a registered lease of at least 30 years; the grant cannot pay for land

Source: PCIDS notification, 4 March 2024.

4. How much the state pays to build a cluster

Block categoryGrant shareMinimum land
B50%25 Acre
C75%25 Acre
D85%15 Acre
  • Cap: Rs 35 crore for clusters up to 50 Acre; Rs 45 crore above 50 Acre. The 2023 policy notification mentions up to Rs 50 crore for private agencies, so confirm the cap that applies on the date you apply.
  • B-category share: grants to B-category blocks are capped at 20% of the PCIDS budget.
  • What counts: project cost excludes land, preliminary and pre-operative expenses and working capital margin. Basic infrastructure can be at most 60% of the eligible cost.
  • Release: 35%, then 40%, then 25%, applied for within 10, 18 and 30 months of approval. A late claim loses 1% of the instalment per month, up to 10%.
  • Completion: within 3 years of sanction, extendable by up to 2 years in two steps.

5. What every PADMA cluster must include

Mandatory facilityMinimum
Plug-and-play units10 units, each at least 1,000 Sq.Yd.
Common Facility CentreRs 1 crore to Rs 5 crore
Business development / facilitation centreBuilt-up area of at least 1,500 Sq.Yd.
Exhibition and display centreAt least 1,000 Sq.Yd.

Optional facilities include skill centres, ICT, cold storage, common packaging, zero liquid discharge, a common boiler, a warehouse and a bank or NBFC branch. Source: PCIDS.

6. What a manufacturer gets inside a PADMA cluster

IncentiveAmount
Capital investment subsidy30%, up to Rs 30 lakh
Interest subsidy on term loans6%, up to Rs 20 lakh a year
Designing, branding, marketing and exports50% reimbursement, up to Rs 10 lakh a year
Entrepreneurship acceleration (start-ups)Rs 20 lakh for proof of concept, prototypes and commercialisation
Venture capital fundRevolving fund of up to Rs 3 crore per unit

Source: PADMA notification. Units that take PADMA incentives cannot also claim similar incentives under other state policies.

!

Check your product first

PCIDS-funded clusters may only sell or lease plots to MSMEs making the block's PADMA product. Ask the cluster or the District MSME office which product your target block has before you shortlist a plot.

7. Rules on plots and prices in a funded cluster

  • The implementing agency may sell or lease industrial plots only to MSMEs making PADMA-approved products.
  • It must publish user charges and plot prices on its website.
  • It cannot sell the PADMA enabling infrastructure (the common facilities).
  • Before the third grant instalment, 100% of plots must be allotted and at least 10% of units must be running.
  • The agency maintains the infrastructure for at least 5 years after commissioning and then forms a cluster welfare association.

Prices are set by the implementing agency, not the state. Prices are subject to change and availability.

8. How an implementing agency applies

  1. Submit a concept note online to the Directorate of MSME, Haryana.
  2. Get in-principle approval from the State Level Steering Committee.
  3. Submit a Detailed Project Report.
  4. Get final approval from the SLSC-PADMA, then draw the grant in three instalments against progress.

Source: PCIDS.

9. Where PADMA stands in 2026

  • In July 2026 the Chief Minister announced 10 new industrial clusters under PADMA, according to KNN India (reported).
  • The Chief Secretary described plans for mini industrial parks in all 143 blocks, as reported by The Tribune.
  • Construction World reported a private park accredited under PADMA in 2026; accreditation claims should be confirmed with the Directorate of MSME.
  • Haryana adopted the Make in Haryana Industrial Policy 2026 in May 2026. A summary by ICAI's MSME committee notes that schemes already in the pipeline continue under earlier guidelines; check whether PADMA incentives have been revised for new units.

10. PADMA cluster or HSIIDC estate?

PADMA clusterHSIIDC estate / IMT
LocationEvery block, including rural onesMostly along highways and near cities
Size25–100 AcreHundreds to thousands of Acre
Who can buyMSMEs making the block's product (in PCIDS clusters)Any eligible industry
Unit incentivesPADMA subsidies inside the clusterState industrial policy incentives
How plots are soldBy HSIIDC or the implementing agencyHSIIDC e-auction at reserve price

For HSIIDC estates and their 2026-27 reserve prices, see our HSIIDC guide.

11. Common mistakes

  • Assuming any unit can buy: funded clusters are tied to the block's product.
  • Using the grant for land: PCIDS excludes land cost; land is the agency's contribution.
  • Missing claim windows: each grant instalment has a deadline, with a deduction for delay.
  • Double-claiming incentives: PADMA unit incentives cannot be stacked with similar state incentives.

12. Glossary

  • PCIDS: PADMA Cluster Infrastructure Development Scheme, the grant for building clusters.
  • Implementing Agency (IA): the body that builds and runs a PADMA cluster.
  • Block category (A/B/C/D): Haryana's classification of blocks by industrial development; less developed blocks get higher grants.
  • SLSC: State Level Steering Committee that approves PADMA projects.
  • SIIDS: the state's industrial infrastructure development scheme that funds HSIIDC work.

13. Talk to our industrial land team

Farmland India's industrial land team can shortlist parks across Haryana by plot size, budget and pollution category, and line up site visits. Browse industrial parks listed on Farmland India or compare nearby belts: HSIIDC estates, Rohtak, Ambala–Panchkula.

Frequently Asked Questions

What is the PADMA scheme in Haryana?
Haryana's Programme to Accelerate Development for MSME Advancement, which aims to build an MSME cluster in every block around a chosen product and gives grants and subsidies for it.
How much land does a PADMA cluster need?
At least 25 Acre in B and C category blocks and 15 Acre in D category blocks under PCIDS; the policy envisages 25 to 100 Acre per block.
How much grant does PADMA give to build a cluster?
50% in B blocks, 75% in C blocks and 85% in D blocks, up to Rs 35 crore for clusters up to 50 Acre and Rs 45 crore above that.
Can a private developer build a PADMA cluster?
Yes. Companies, LLPs, partnerships, societies, trusts, cooperatives and FPOs can be Implementing Agencies if they meet the contribution, loan and net-worth conditions.
What incentives do units in a PADMA cluster get?
A 30% capital subsidy up to Rs 30 lakh, a 6% interest subsidy up to Rs 20 lakh a year, and up to Rs 10 lakh a year for design, branding and marketing, among others.
Can any business buy a plot in a PADMA cluster?
In clusters funded under PCIDS, plots can only go to MSMEs making the block's PADMA-approved product.
Who sets plot prices in a PADMA cluster?
The implementing agency, which must publish prices and user charges on its website.
Is PADMA still running after the Make in Haryana policy 2026?
The PCIDS window runs to 16 August 2028 or the policy's validity. Check with the Directorate of MSME for any revisions after the 2026 policy.
Where do I apply?
Implementing agencies submit a concept note online to the Directorate of MSME, Haryana. Units claim incentives through the MSME Directorate.

Sources

Spotted an error? Write to wiki@farmlandindia.com and we will correct it.

Looking for an industrial plot?

Tell us your plot size, budget and pollution category. Our industrial land team will shortlist parks and arrange site visits.

For land buyersMap Layers coming soon

See every Haryana listing on the map

View on mapEvery listing pinned where it actually is. Master plans, survey numbers and boundaries are coming. · Browse the list
For land owners

Own land in Haryana? List it free. Our team calls within 24 hours.

Free for owners, families, lawyers and agents. We review the documents you share before it goes live; they are never published. Use the form

Related reading

← All P22 Industrial Land & Parks guides

Farmland India ("the Platform"), operated by Bulk Procure Private Limited, is a digital marketplace for listing agricultural land, farmhouse and plotted development projects. The Platform is not a real estate broker, agent or intermediary under RERA or any other applicable law, and does not act for either party to a transaction.

Listings are submitted by developers, owners and their authorised representatives. Before publication, the Platform carries out a documentary review of the material supplied and records what was sighted. That review is limited to the documents made available to us at that time. It is not a title investigation, not a legal opinion, and not a warranty of title, approvals, or the accuracy of any information supplied by a lister. The Trust Score is an internal assessment produced from that review and is intended as a research aid, not as a guarantee of outcome.

Every buyer must carry out independent due diligence before any transaction — including verification of land records, encumbrance searches, approvals and regulatory compliance — through their own advocate and chartered accountant. Any legal or advisory professional introduced through the Platform is engaged directly by the user, on that professional's own terms; the Platform does not employ, supervise or accept responsibility for their work.

Nothing on the Platform is investment advice. Land values can fall as well as rise. The Platform is not liable for any loss, dispute or damage arising from a transaction between parties.