BHAVYA Scheme: Central Funding for 100 Industrial Parks, Rules and How to Apply
The Rs 33,660 crore Bharat Audyogik Vikas Yojana explained from DPIIT's guidelines: eligibility, land, funding, scoring, tranches and the Round 2 deadline.
BHAVYA, the Bharat Audyogik Vikas Yojana, is the Centre's Rs 33,660 crore scheme to fund 100 plug-and-play industrial parks between 2026-27 and 2031-32. It does not sell plots to factories. It pays for the roads, utilities, effluent plants, worker housing and other infrastructure inside parks that a State, a central public sector enterprise or a private developer brings forward. Last checked against official sources on 17 November 2026.
1. Key facts
| Item | Detail | Source |
|---|---|---|
| Scheme | Bharat Audyogik Vikas Yojana (BHAVYA), a Central Sector scheme of DPIIT | DPIIT guidelines |
| Approved / notified | Cabinet approval 18 March 2026; notified 10 April 2026 | PIB; Vikaspedia |
| Outlay | Rs 33,660 crore, including Rs 60 crore for administration | PIB; DPIIT guidelines |
| Target | 100 parks over six years, 2026-27 to 2031-32; up to 50 in Phase 1 | DPIIT guidelines |
| Park size | 100 to 1,000 Acre; 25 Acre minimum in hill states, the North East and smaller UTs | DPIIT guidelines, para 4 |
| Central support | Up to Rs 1 crore per Acre (about Rs 2,066 per Sq.Yd. of park area) | PIB; DPIIT guidelines, para 9 |
| Who applies | States and UTs, central public sector enterprises, and private developers through a State-backed SPV | DPIIT guidelines, paras 5 and 7 |
| Implementing agency | NICDC as Project Management Agency; funds routed through NICDIT | DPIIT guidelines |
| Phase 1, Round 2 deadline | 30 November 2026 (extended) | NICDC website |
2. What BHAVYA is, in plain terms
Most Indian industrial estates are built by State agencies such as HSIIDC, UPSIDA or RIICO, out of their own budgets. BHAVYA adds central money to that model. It builds on the industrial smart cities of the National Industrial Corridor Development Programme, and the PIB release of 18 March 2026 says the parks will follow PM GatiShakti planning so that road, rail, port and air links are considered from the start.
- Plug-and-play: the aim is that a factory can take a plot with roads, power, water, drainage and approvals already in place, rather than waiting years for the estate to be finished.
- Challenge mode: proposals compete. Each is scored out of 100, and only those above a benchmark set by the national committee are taken up.
- Land is the sponsor's contribution: the State or developer puts in the land as equity in a project company (an SPV). The Centre puts in money for infrastructure.
- Not a subsidy to units: individual manufacturers do not apply to BHAVYA. They benefit later, as allottees inside a funded park.
3. Who can apply
Under para 5 of the DPIIT guidelines, a proposal must be sponsored by one of the following:
- A State or Union Territory, on the recommendation of its State Level Committee chaired by the Chief Secretary.
- A central public sector enterprise, with the approval of its Board.
- A private developer, through a joint venture SPV with the State Nodal Agency and NICDIT. The State still sponsors the proposal.
Each park needs one application with a Detailed Project Report (DPR) in the format at Annexure II, filed on the portal run by NICDC. The national committee can cap how many parks one State receives.
4. Land rules
- Minimum size: 100 Acre of contiguous land, or no more than two parcels of at least 100 Acre each within 2 km of one another.
- Smaller parks: 25 Acre is enough in Himachal Pradesh, Uttarakhand, the North Eastern States, Delhi, Goa, Jammu and Kashmir, Ladakh and the smaller UTs.
- Large parks: up to 20 parks of 500 to 1,000 Acre. Funding is capped at 1,000 Acre even if the park is bigger.
- Possession: at least 90% of the land must be free of encumbrances and in the sponsor's possession when it applies.
- Transfer: the land must move to the SPV within three months of approval, or the approval lapses. The national committee can allow three more months.
- Planning powers: the State must delegate planning and development powers to the SPV before any money is released.
- Land pooling: land assembled through pooling or town planning schemes earns 5 extra marks.
- Brownfield parks: considered case by case.
Land is valued at the higher of the circle rate (DLC rate in Rajasthan) or a fair market value fixed by a valuation committee. Where land was acquired, its cost is the compensation paid plus interest under the 2013 land acquisition law; premiums, enhanced compensation, stamp duty and finance costs are excluded.
5. How much the Centre pays, and for what
| Route | Central support | Form |
|---|---|---|
| State, UT or CPSE-led park | Up to Rs 1 crore per Acre (about Rs 2,066 per Sq.Yd.) | Equity in the SPV, plus debt where approved |
| Private-developer-led park | Lower of Rs 50 lakh per Acre (about Rs 1,033 per Sq.Yd.) or 50% of infrastructure cost | Equity only |
| External infrastructure | Up to 25% of the BHAVYA funding and 25% of the external cost | State funds the rest under its State Support Agreement |
NICDIT's equity cannot exceed the value of the land put in, and cannot exceed 50% of the SPV's paid-up capital. The funding approved is not revised later. Annexure III of the guidelines lists what the money can pay for:
- Core infrastructure: internal roads with footpaths, underground utilities, storm water drains, street lights, landscaping, CETP, WTP, STP, solid waste management, ICT and security, an administrative block and fire safety.
- Value-added infrastructure: built-to-suit sheds, warehousing, testing labs, R&D and training centres, and renewable energy.
- Social infrastructure: worker housing, common facility centres, day care and health services, and skill centres.
- External infrastructure: the link road to a highway, rail head or logistics hub; the power line from the nearest substation; the water pipeline; and gas supply.
6. How proposals are scored
Annexure I of the guidelines scores each proposal out of 100. The weights show what the Centre values:
| Criterion | Max marks |
|---|---|
| Distance from a city of at least 1 lakh people (50,000 in hill and NE States) | 10 |
| Land through pooling or a town planning scheme | 5 |
| Within 10 km of a National Highway, 5 km of a State Highway, 15 km of an ICD or logistics park, or 25 km of a port or cargo airport | 10 |
| Approach road of at least 24 m right of way (18 m in hill States) | 5 |
| Confirmed power and water supply for projected demand | 10 |
| DPR quality and industrial competitiveness | 25 |
| Low vacancy in competing industrial areas within 100 km | 5 |
| Demand assessment with supporting evidence | 5 |
| Approvals mapped onto the SPV's single window | 10 |
| Industrial power tariff close to domestic tariff; renewable energy | 10 |
| Time taken to allot industrial land in the last calendar year | 5 |
| States with per capita income below the national average | 10 |
Two criteria matter for anyone watching existing estates. The vacancy test rewards regions where nearby non-SEZ industrial areas are at least 85% occupied. The allotment-speed test gives full marks only where the State issued allotment letters within 60 days of application last year. Both push States to show real demand and quick allotment before they ask for more land.
7. How the money is released
Funds go out in three tranches of 40%, 40% and 20% over about three years, each tied to conditions in para 9.6:
| Tranche | Share | Conditions |
|---|---|---|
| I (a) | 30% | Approval; 90% of land transferred to the SPV; planning powers delegated; power and water allocated |
| I (b) | 10% | Environmental clearance obtained and works started |
| II | 40% | 75% of Tranche I used; physical progress; plots allotted to at least two manufacturing units (Rs 50 crore commitment in most States, Rs 10 crore in hill and NE States); for private-led parks, the State Support Agreement signed |
| III (a) | 10% | 90% of earlier funds used; external infrastructure complete; at least two factories under construction |
| III (b) | 10% | Final completion certificate |
Phase 1 parks are to be selected within a year of notification. Core works are expected within 24 months of approval, with more time for parks of 500 to 1,000 Acre.
8. The private developer route
Annexure VI sets extra conditions for private developers. These are the ones most often missed:
- Incorporation: a company registered in India. In a consortium, the lead member must hold at least 26%.
- Net worth: positive net worth of at least 15% of project cost, certified by a Chartered Accountant from the last audited accounts.
- Experience: at least one completed industrial estate, industrial or logistics park, SEZ or large infrastructure project of 50 Acre or more in the last ten years.
- Clean record: not debarred or blacklisted by any government authority in the last three years.
- SPV stake: at least 26% equity, mainly as land. NICDIT's equity equals the infrastructure cost within Rs 50 lakh per Acre.
- Board: at least five directors; the Chairperson is the State Nodal Agency's nominee; the developer can nominate no more than two.
- Deadlines after approval: shareholders' agreement within 60 days; State Support Agreement within 90 days.
- Lock-in: five years from the completion certificate, which needs core works done, plots allotted to five units and two units in production.
- Exit: after lock-in, the State Nodal Agency and NICDIT get 90 days' right of first refusal at the higher of the offer price or fair market value.
Anchor investors
A developer that is also an anchor investor may allot itself up to 25% of developed land, on terms no better than other allottees, if it commits at least Rs 50 crore (Rs 10 crore in hill and NE States). The other 75% or more must be allotted through a transparent process.
9. What BHAVYA means if you want a plot
- You will deal with the SPV, not DPIIT. Allotment, lease terms and pricing follow the SPV's own land allotment and pricing policy, approved as part of the project.
- Plots will be leasehold. The guidelines speak of allotment and lease of plots; expect lease deeds, building timelines and resumption if you do not build.
- Infrastructure should arrive earlier. Because money is released against progress, roads and utilities are tied to milestones rather than open-ended budgets.
- Approvals through one window. Parks score marks for mapping land, building, utilities, fire, pollution and labour approvals onto the SPV's single window.
- Timing. Phase 1 parks will be selected in 2026-27 and built over about two years. Plots in BHAVYA parks are unlikely to be available before 2028 at the earliest. If you need land now, an existing State estate is the practical choice.
10. Who should act before 30 November 2026
- State industrial agencies with 100 Acre or more already in possession and power and water confirmed. Round 2 also accepts revised proposals that were not selected in Round 1.
- Central public sector enterprises with surplus land near highways or ports, with Board approval in hand.
- Private park developers who meet the net worth and 50 Acre experience tests and have a State Nodal Agency willing to sponsor them.
- Landowner groups considering land pooling with a State agency: pooled land earns extra marks, but only the State can apply.
Applications filed after the deadline will wait for Phase 2, which covers the remaining 50 parks. Check the NICDC website for any further notice before filing.
11. DPR checklist (Annexure II)
- Executive summary, project background, proponent and rationale.
- Site, district profile, industrial scenario, promoters and development mode (private, public or PPP).
- Location and connectivity by rail, road, air and port; site analysis; environmental clearance; external utilities.
- Master plan: zoning, land use, roads and right of way, drainage, water supply and treatment, sewage, solid waste, power, telecom, landscaping, warehousing, worker housing.
- Project cost, cost of land, means of finance and the grant sought.
- Financial analysis: revenue and expenditure assumptions, O&M plan and recovery of O&M costs, key financial indicators.
- Implementation strategy, including how plots and sheds will be allotted.
- Demand assessment: target sectors, demand validation and manpower.
- Expected private investment, number of units and employment.
- Supporting documents: government orders, notifications, PM GatiShakti screenshots and DPR extracts.
12. Common mistakes
- Applying with land not yet in possession. The 90% possession test applies on the day of application, not at approval.
- Leaving older park issues open. Pending issues in NICDP or PM MITRA parks in the same State, such as delegation of powers or external connectivity, must be resolved before applying.
- A demand study without evidence. Unsupported demand assessments score lower; vacancy data for estates within 100 km is needed.
- Assuming funding will be topped up. Approved funding is not revised, so cost estimates need to be realistic from the start.
- Double funding. Convergence with other schemes is encouraged, but the same component cannot be funded twice.
13. Glossary
- DPIIT: Department for Promotion of Industry and Internal Trade, the ministry department that owns the scheme.
- NICDC: National Industrial Corridor Development Corporation, the Project Management Agency.
- NICDIT: National Industrial Corridor Development and Implementation Trust, which holds the Centre's equity in the SPVs.
- NLSC / SLC: the National Level Steering Committee chaired by the Secretary, DPIIT, and each State's Level Committee chaired by the Chief Secretary.
- SPV: the project company under the Companies Act, 2013 that owns the land, builds the park and allots plots.
- SSA: State Support Agreement, the State's commitments on powers, external infrastructure and clearances.
14. Talk to our industrial land team
Farmland India's industrial land team can shortlist parks in Haryana, Uttar Pradesh and Rajasthan by plot size, budget and pollution category, and line up site visits. Browse industrial parks listed on Farmland India or compare nearby belts: HSIIDC estates, UPSIDA, RIICO Bhiwadi, Noida.
Frequently Asked Questions
What is the BHAVYA scheme?
Can a factory owner apply for BHAVYA funding?
How much funding does BHAVYA give per Acre?
What is the minimum land for a BHAVYA park?
What is the last date to apply?
Who implements BHAVYA?
How are BHAVYA proposals selected?
Can a private developer get BHAVYA funding?
When will plots in BHAVYA parks be available?
Is BHAVYA the same as the PM MITRA or NICDP parks?
Sources
- PIB: Cabinet approves BHAVYA (18 March 2026)
- DPIIT: BHAVYA scheme guidelines, hosted by NICDC (PDF)
- NICDC: website, BHAVYA notices and Round 2 deadline
- PM India: Cabinet approves BHAVYA
- Vikaspedia: Bharat Audyogik Vikas Yojana (BHAVYA)
- KNN India: deadline extended to 31 October (October 2026, reported)
- News Arena: four-month application window for 50 parks (May 2026, reported)
Spotted an error? Write to wiki@farmlandindia.com and we will correct it.