BHAVYA Scheme: Central Funding for 100 Industrial Parks, Rules and How to Apply

The Rs 33,660 crore Bharat Audyogik Vikas Yojana explained from DPIIT's guidelines: eligibility, land, funding, scoring, tranches and the Round 2 deadline.

Farmland India Reviewed ยท Updated 14 November 2026 ยท Official sources linked below
Rs 33,660 cr
Total outlay
100
Parks by 2031-32
Rs 1 cr
Per Acre, maximum support
30 Nov 2026
Round 2 deadline

BHAVYA, the Bharat Audyogik Vikas Yojana, is the Centre's Rs 33,660 crore scheme to fund 100 plug-and-play industrial parks between 2026-27 and 2031-32. It does not sell plots to factories. It pays for the roads, utilities, effluent plants, worker housing and other infrastructure inside parks that a State, a central public sector enterprise or a private developer brings forward. Last checked against official sources on 17 November 2026.

bhavya schemebharat audyogik vikas yojanabhavya scheme guidelinesbhavya industrial parksbhavya scheme dpiitplug and play industrial parks100 industrial parks schemebhavya scheme eligibilitybhavya scheme last datebhavya scheme private developerbhavya scheme evaluation criteriabhavya dpr templatenicdc bhavyaindustrial park scheme 2026central scheme for industrial parksbhavya scheme fundingbhavya spvindustrial park development scheme indiabhavya anchor investorbhavya scheme round 2

1. Key facts

ItemDetailSource
SchemeBharat Audyogik Vikas Yojana (BHAVYA), a Central Sector scheme of DPIITDPIIT guidelines
Approved / notifiedCabinet approval 18 March 2026; notified 10 April 2026PIB; Vikaspedia
OutlayRs 33,660 crore, including Rs 60 crore for administrationPIB; DPIIT guidelines
Target100 parks over six years, 2026-27 to 2031-32; up to 50 in Phase 1DPIIT guidelines
Park size100 to 1,000 Acre; 25 Acre minimum in hill states, the North East and smaller UTsDPIIT guidelines, para 4
Central supportUp to Rs 1 crore per Acre (about Rs 2,066 per Sq.Yd. of park area)PIB; DPIIT guidelines, para 9
Who appliesStates and UTs, central public sector enterprises, and private developers through a State-backed SPVDPIIT guidelines, paras 5 and 7
Implementing agencyNICDC as Project Management Agency; funds routed through NICDITDPIIT guidelines
Phase 1, Round 2 deadline30 November 2026 (extended)NICDC website

2. What BHAVYA is, in plain terms

Most Indian industrial estates are built by State agencies such as HSIIDC, UPSIDA or RIICO, out of their own budgets. BHAVYA adds central money to that model. It builds on the industrial smart cities of the National Industrial Corridor Development Programme, and the PIB release of 18 March 2026 says the parks will follow PM GatiShakti planning so that road, rail, port and air links are considered from the start.

  • Plug-and-play: the aim is that a factory can take a plot with roads, power, water, drainage and approvals already in place, rather than waiting years for the estate to be finished.
  • Challenge mode: proposals compete. Each is scored out of 100, and only those above a benchmark set by the national committee are taken up.
  • Land is the sponsor's contribution: the State or developer puts in the land as equity in a project company (an SPV). The Centre puts in money for infrastructure.
  • Not a subsidy to units: individual manufacturers do not apply to BHAVYA. They benefit later, as allottees inside a funded park.

3. Who can apply

Under para 5 of the DPIIT guidelines, a proposal must be sponsored by one of the following:

  • A State or Union Territory, on the recommendation of its State Level Committee chaired by the Chief Secretary.
  • A central public sector enterprise, with the approval of its Board.
  • A private developer, through a joint venture SPV with the State Nodal Agency and NICDIT. The State still sponsors the proposal.

Each park needs one application with a Detailed Project Report (DPR) in the format at Annexure II, filed on the portal run by NICDC. The national committee can cap how many parks one State receives.

4. Land rules

  • Minimum size: 100 Acre of contiguous land, or no more than two parcels of at least 100 Acre each within 2 km of one another.
  • Smaller parks: 25 Acre is enough in Himachal Pradesh, Uttarakhand, the North Eastern States, Delhi, Goa, Jammu and Kashmir, Ladakh and the smaller UTs.
  • Large parks: up to 20 parks of 500 to 1,000 Acre. Funding is capped at 1,000 Acre even if the park is bigger.
  • Possession: at least 90% of the land must be free of encumbrances and in the sponsor's possession when it applies.
  • Transfer: the land must move to the SPV within three months of approval, or the approval lapses. The national committee can allow three more months.
  • Planning powers: the State must delegate planning and development powers to the SPV before any money is released.
  • Land pooling: land assembled through pooling or town planning schemes earns 5 extra marks.
  • Brownfield parks: considered case by case.

Land is valued at the higher of the circle rate (DLC rate in Rajasthan) or a fair market value fixed by a valuation committee. Where land was acquired, its cost is the compensation paid plus interest under the 2013 land acquisition law; premiums, enhanced compensation, stamp duty and finance costs are excluded.

5. How much the Centre pays, and for what

RouteCentral supportForm
State, UT or CPSE-led parkUp to Rs 1 crore per Acre (about Rs 2,066 per Sq.Yd.)Equity in the SPV, plus debt where approved
Private-developer-led parkLower of Rs 50 lakh per Acre (about Rs 1,033 per Sq.Yd.) or 50% of infrastructure costEquity only
External infrastructureUp to 25% of the BHAVYA funding and 25% of the external costState funds the rest under its State Support Agreement

NICDIT's equity cannot exceed the value of the land put in, and cannot exceed 50% of the SPV's paid-up capital. The funding approved is not revised later. Annexure III of the guidelines lists what the money can pay for:

  • Core infrastructure: internal roads with footpaths, underground utilities, storm water drains, street lights, landscaping, CETP, WTP, STP, solid waste management, ICT and security, an administrative block and fire safety.
  • Value-added infrastructure: built-to-suit sheds, warehousing, testing labs, R&D and training centres, and renewable energy.
  • Social infrastructure: worker housing, common facility centres, day care and health services, and skill centres.
  • External infrastructure: the link road to a highway, rail head or logistics hub; the power line from the nearest substation; the water pipeline; and gas supply.

6. How proposals are scored

Annexure I of the guidelines scores each proposal out of 100. The weights show what the Centre values:

CriterionMax marks
Distance from a city of at least 1 lakh people (50,000 in hill and NE States)10
Land through pooling or a town planning scheme5
Within 10 km of a National Highway, 5 km of a State Highway, 15 km of an ICD or logistics park, or 25 km of a port or cargo airport10
Approach road of at least 24 m right of way (18 m in hill States)5
Confirmed power and water supply for projected demand10
DPR quality and industrial competitiveness25
Low vacancy in competing industrial areas within 100 km5
Demand assessment with supporting evidence5
Approvals mapped onto the SPV's single window10
Industrial power tariff close to domestic tariff; renewable energy10
Time taken to allot industrial land in the last calendar year5
States with per capita income below the national average10

Two criteria matter for anyone watching existing estates. The vacancy test rewards regions where nearby non-SEZ industrial areas are at least 85% occupied. The allotment-speed test gives full marks only where the State issued allotment letters within 60 days of application last year. Both push States to show real demand and quick allotment before they ask for more land.

7. How the money is released

Funds go out in three tranches of 40%, 40% and 20% over about three years, each tied to conditions in para 9.6:

TrancheShareConditions
I (a)30%Approval; 90% of land transferred to the SPV; planning powers delegated; power and water allocated
I (b)10%Environmental clearance obtained and works started
II40%75% of Tranche I used; physical progress; plots allotted to at least two manufacturing units (Rs 50 crore commitment in most States, Rs 10 crore in hill and NE States); for private-led parks, the State Support Agreement signed
III (a)10%90% of earlier funds used; external infrastructure complete; at least two factories under construction
III (b)10%Final completion certificate

Phase 1 parks are to be selected within a year of notification. Core works are expected within 24 months of approval, with more time for parks of 500 to 1,000 Acre.

8. The private developer route

Annexure VI sets extra conditions for private developers. These are the ones most often missed:

  • Incorporation: a company registered in India. In a consortium, the lead member must hold at least 26%.
  • Net worth: positive net worth of at least 15% of project cost, certified by a Chartered Accountant from the last audited accounts.
  • Experience: at least one completed industrial estate, industrial or logistics park, SEZ or large infrastructure project of 50 Acre or more in the last ten years.
  • Clean record: not debarred or blacklisted by any government authority in the last three years.
  • SPV stake: at least 26% equity, mainly as land. NICDIT's equity equals the infrastructure cost within Rs 50 lakh per Acre.
  • Board: at least five directors; the Chairperson is the State Nodal Agency's nominee; the developer can nominate no more than two.
  • Deadlines after approval: shareholders' agreement within 60 days; State Support Agreement within 90 days.
  • Lock-in: five years from the completion certificate, which needs core works done, plots allotted to five units and two units in production.
  • Exit: after lock-in, the State Nodal Agency and NICDIT get 90 days' right of first refusal at the higher of the offer price or fair market value.
!

Anchor investors

A developer that is also an anchor investor may allot itself up to 25% of developed land, on terms no better than other allottees, if it commits at least Rs 50 crore (Rs 10 crore in hill and NE States). The other 75% or more must be allotted through a transparent process.

9. What BHAVYA means if you want a plot

  • You will deal with the SPV, not DPIIT. Allotment, lease terms and pricing follow the SPV's own land allotment and pricing policy, approved as part of the project.
  • Plots will be leasehold. The guidelines speak of allotment and lease of plots; expect lease deeds, building timelines and resumption if you do not build.
  • Infrastructure should arrive earlier. Because money is released against progress, roads and utilities are tied to milestones rather than open-ended budgets.
  • Approvals through one window. Parks score marks for mapping land, building, utilities, fire, pollution and labour approvals onto the SPV's single window.
  • Timing. Phase 1 parks will be selected in 2026-27 and built over about two years. Plots in BHAVYA parks are unlikely to be available before 2028 at the earliest. If you need land now, an existing State estate is the practical choice.

10. Who should act before 30 November 2026

  1. State industrial agencies with 100 Acre or more already in possession and power and water confirmed. Round 2 also accepts revised proposals that were not selected in Round 1.
  2. Central public sector enterprises with surplus land near highways or ports, with Board approval in hand.
  3. Private park developers who meet the net worth and 50 Acre experience tests and have a State Nodal Agency willing to sponsor them.
  4. Landowner groups considering land pooling with a State agency: pooled land earns extra marks, but only the State can apply.

Applications filed after the deadline will wait for Phase 2, which covers the remaining 50 parks. Check the NICDC website for any further notice before filing.

11. DPR checklist (Annexure II)

  • Executive summary, project background, proponent and rationale.
  • Site, district profile, industrial scenario, promoters and development mode (private, public or PPP).
  • Location and connectivity by rail, road, air and port; site analysis; environmental clearance; external utilities.
  • Master plan: zoning, land use, roads and right of way, drainage, water supply and treatment, sewage, solid waste, power, telecom, landscaping, warehousing, worker housing.
  • Project cost, cost of land, means of finance and the grant sought.
  • Financial analysis: revenue and expenditure assumptions, O&M plan and recovery of O&M costs, key financial indicators.
  • Implementation strategy, including how plots and sheds will be allotted.
  • Demand assessment: target sectors, demand validation and manpower.
  • Expected private investment, number of units and employment.
  • Supporting documents: government orders, notifications, PM GatiShakti screenshots and DPR extracts.

12. Common mistakes

  • Applying with land not yet in possession. The 90% possession test applies on the day of application, not at approval.
  • Leaving older park issues open. Pending issues in NICDP or PM MITRA parks in the same State, such as delegation of powers or external connectivity, must be resolved before applying.
  • A demand study without evidence. Unsupported demand assessments score lower; vacancy data for estates within 100 km is needed.
  • Assuming funding will be topped up. Approved funding is not revised, so cost estimates need to be realistic from the start.
  • Double funding. Convergence with other schemes is encouraged, but the same component cannot be funded twice.

13. Glossary

  • DPIIT: Department for Promotion of Industry and Internal Trade, the ministry department that owns the scheme.
  • NICDC: National Industrial Corridor Development Corporation, the Project Management Agency.
  • NICDIT: National Industrial Corridor Development and Implementation Trust, which holds the Centre's equity in the SPVs.
  • NLSC / SLC: the National Level Steering Committee chaired by the Secretary, DPIIT, and each State's Level Committee chaired by the Chief Secretary.
  • SPV: the project company under the Companies Act, 2013 that owns the land, builds the park and allots plots.
  • SSA: State Support Agreement, the State's commitments on powers, external infrastructure and clearances.

14. Talk to our industrial land team

Farmland India's industrial land team can shortlist parks in Haryana, Uttar Pradesh and Rajasthan by plot size, budget and pollution category, and line up site visits. Browse industrial parks listed on Farmland India or compare nearby belts: HSIIDC estates, UPSIDA, RIICO Bhiwadi, Noida.

Frequently Asked Questions

What is the BHAVYA scheme?
The Bharat Audyogik Vikas Yojana is a Rs 33,660 crore central scheme, approved on 18 March 2026, to fund infrastructure in 100 plug-and-play industrial parks from 2026-27 to 2031-32.
Can a factory owner apply for BHAVYA funding?
No. Proposals come from States and UTs, central public sector enterprises, or private developers through a State-backed SPV. Factories benefit as allottees in funded parks.
How much funding does BHAVYA give per Acre?
Up to Rs 1 crore per Acre (about Rs 2,066 per Sq.Yd.) for State, UT or CPSE-led parks. Private-developer-led parks get the lower of Rs 50 lakh per Acre or 50% of infrastructure cost.
What is the minimum land for a BHAVYA park?
100 Acre, contiguous or in up to two parcels within 2 km. In hill States, the North East and smaller UTs the minimum is 25 Acre.
What is the last date to apply?
The NICDC website shows the Phase 1, Round 2 deadline extended to 30 November 2026. KNN had reported an earlier extension to 31 October 2026.
Who implements BHAVYA?
DPIIT owns the scheme. NICDC is the Project Management Agency, and the Centre's equity is held through NICDIT.
How are BHAVYA proposals selected?
In challenge mode. Each proposal is scored out of 100 on connectivity, utilities, DPR quality, demand, single-window approvals, power tariff, allotment speed and State income, and must clear a benchmark score.
Can a private developer get BHAVYA funding?
Yes, through a joint venture SPV with the State Nodal Agency and NICDIT, if it meets the net worth, experience and clean-record tests in Annexure VI.
When will plots in BHAVYA parks be available?
Phase 1 parks are selected in 2026-27 and works are expected within about 24 months, so plots are unlikely before 2028. Each SPV will publish its own allotment policy.
Is BHAVYA the same as the PM MITRA or NICDP parks?
No. They are separate programmes. BHAVYA builds on the NICDP model, and States must settle pending issues in NICDP and PM MITRA parks before applying.

Sources

Spotted an error? Write to wiki@farmlandindia.com and we will correct it.

Looking for an industrial plot?

Tell us your plot size, budget and pollution category. Our industrial land team will shortlist parks and arrange site visits.

Related reading

โ† All P22 Industrial Land & Parks guides

Farmland India ("the Platform"), operated by Bulk Procure Private Limited, is a digital marketplace for listing agricultural land, farmhouse and plotted development projects. The Platform is not a real estate broker, agent or intermediary under RERA or any other applicable law, and does not act for either party to a transaction.

Listings are submitted by developers, owners and their authorised representatives. Before publication, the Platform carries out a documentary review of the material supplied and records what was sighted. That review is limited to the documents made available to us at that time. It is not a title investigation, not a legal opinion, and not a warranty of title, approvals, or the accuracy of any information supplied by a lister. The Trust Score is an internal assessment produced from that review and is intended as a research aid, not as a guarantee of outcome.

Every buyer must carry out independent due diligence before any transaction โ€” including verification of land records, encumbrance searches, approvals and regulatory compliance โ€” through their own advocate and chartered accountant. Any legal or advisory professional introduced through the Platform is engaged directly by the user, on that professional's own terms; the Platform does not employ, supervise or accept responsibility for their work.

Nothing on the Platform is investment advice. Land values can fall as well as rise. The Platform is not liable for any loss, dispute or damage arising from a transaction between parties.